7 St. Andrews Way

7 St. Andrews Way, Bow The works involved dilapidation repairs to an existing factory / warehouse / office space. The roof was upgraded to improve the EPC rating along with upgrading of lighting, Air Handling, AC, lift refurbishment and decorative finishes inside and out. Date : 2020 Budget / Cost : £1.1m Client : CCLA…

Calouste Galbenkian Gallery

Calouste Galbenkian Gallery & Foundation 50 Hoxton Square, London N1 6PB Fit out of developers shell to create an Art Gallery and office space. Client:  Calouste Gulbenkian Foundation (UK Branch) Architect/surveyor:  Theis & Khan Architects Cost/value:  £780k Calouste_Gulbenkian_Foundation_UK_BranchGulbenkian_UK0909CAGU01 – UK Headquarters 024

22 Bardsley Lane

22 Bardsley Lane 22 Bardsley Lane, Greenwich, London SE10 9RF This project involved the strip out of an old morturary and the creation of high quality offices to the ground floor, with a luxury flat to the first floor.  Works included structural alterations, new services and the installation of large glazed screens and windows. Client: …

Block 5 Leathermarket

Block 5 Block 5 Leathermarket, London SE1 The project involved the strip out of old office/garage areas including removal of strong room and safe. The structural removal of the garage entrance and reforming to suit new design. Installation of new ceilings, partitions, finishes and all services to a high standard. With the enhancement of warehouse features…

198 Railton Road

198 Railton RoadThe works involved the reconfiguration of the existing 1960’s built single storey building, extension to the rear and the addition of two new floors added to provide new gallery space, adaptable workshops and open plan office space for a community charity.Date : 2019-2020Budget : £965kClient : 198 Contemporary Arts & Learning www.198.org.ukQS :…

George West House

George West House 2-3 Clapham Common North Side, London SW4 This project involved the stripping out of an existing 4 storey building, carrying out structural repairs, constructing two roof-top extensions and fitting out the building to create a high-quality head office for a computer software company Date:  2000 Duration: 18 months Budget/cost:  £4.5M Client:  QAS…

The Print Rooms

The Print Rooms The Print Rooms, Union Street, London, SE1 Dollman Ralston stripped out a basement space to create an open plan office space complete with new M&E package, sand blasting walls, floor levelling and herringbone Maple herringbone flooring. New fire rated glazed doors and windows were installed to provide a modern office space. Date:…

Guild House

Guild House Rollions Road, London SE15 New steel framed office extension on top of an existing three storey warehouse building. Client:  Renewal Group Ltd. Architect/Surveyor:  DBK Architects Value/Cost:  £490k Date:  2013-14 001__RR_0212002__RR_0213004__RR_0218010__RR_0233015__RR_0263017__RR_0281018__RR_0289019__RR_0298027__RR_0363032__RR_0325037__RR_0340041__RR_0387045__RR_0421047__RR_0431048__RR_0434050__RR_0445052__RR_0461053__RR_0470054__RR_0482057__RR_0494060__RR_0521

Canalot Studios

Canelot Studios Kensell Road, London W10 This project involved the refurbishment of the common parts of a large Victorian warehouse that was used as offices for small companies involved in the media industry. A new reception area was made by cutting a large opening through a structural wall and the entrance was opened up and…

Chinatown

Chinatown 10-11 Gerrard Street, London WC2 Roof extension and formation of four new luxury flats, plus structural works to form a triple-level commercial restaurant space. Date:  2017 Budget/cost:  £1.7M Client:  Shaftesbury Chinatown Ltd. Architect/surveyor:  Fresson & Tee 10-11 Gerrard Street10-11 Gerrard Street Kitchen10-11 Gerrard Street Joinery